Industrial Site Development

Renton, WA

Principal-in-charge: Chevy Chase, PE, SE
Civil Project Manager: Jared Underbrink, PE
Planner: Carmel Gregory

Project Elements:
Critical area easement
Consultant coordination
Land use entitlements

CG Engineering managed permitting and consultant coordination for pre-development of a 4.4-acre industrial site for a commercial developer and helped transition it to a hospital use when it was sold during permitting to a healthcare developer. Our planning role included managing the recording of a critical area easement to protect an on-site wetland, consultant coordination, and managing land use entitlements and permitting with multiple jurisdictions.

Contact Us

250 4th Ave S Suite 200 Edmonds, WA 98020

1910 Bickford Ave Suite G Snohomish, WA 98290

425.778.8500