Mercedes Benz of Lynnwood
Lynnwood, WAPrincipal-in-charge: Chevy Chase, PE, SE
Structural Project Manager: Joe Galusha, PE, SE
Civil Project Manager: Jared Underbrink, PE
Structural Elements:
Detention vaults
Steel framed construction
Civil Elements:
Low-impact design
Stormwater management
CG Engineering provided civil and structural engineering for a new Mercedes Benz dealership in the City of Lynnwood. The building is one-story, approximately 42,000 square feet with a showroom, a service area and a small mezzanine. The showroom area is a 35 foot tall steel framed structure with a metal deck roof. The site is approximately 3.5 acres and has a critical area. To handle increased flows due to the addition of impervious areas, a structural detention vault was designed. To minimize the size and cost of the vault, rain gardens were designed to account for significant portions of the site runoff.