Woodinville Commerical Center
Woodinville, WAPrincipal-in-charge: Greg Guillen, PE, SE
Civil Project Manager: Jared Underbrink, PE
Civil Elements:
3.1 acre site
Temporary Erosion Control plans
Stormwater management
Sewer and water connections
Street Improvements and Traffic Control Plans
Permitting and Environmental Mitigation for Type 3 stream
CG Engineering provided the civil design for this commercial center of 4 buildings with associated driveways and parking areas . We worked closely with the architect, surveyor, wetland ecologist, and geotechnical engineer during design. CG contracted with a wetland biologist to assist in a stream restoration and enhancement plan to mitigate adverse impacts as a result of construction.